Project Area
4,6 Ha of 20 sub-district in 5 district in Northern & Central jakarta
Capacity WWTP
109.000 m³/day
Population Coverage
696.849 PE
Location WWTP
Nort side of Waduk Sunter Utara
Total of pipe leght
458.775 m
Diameter Ø
200 - 2000 mm
Scope of Work