potential projects

LRT Jakarta Phase 2A





Project Overview

LRT Jakarta Phase 1A started operating in 2019 and has a 5.8 km (3.6 mi) line serving six stations, from Pegangsaan Dua in North Jakarta to Velodrome in East Jakarta. It is going to be extended 6.4 km to Manggarai from Velodrome, which will be finished in 2026, so it will have a total distance of 12.2 km.

LRT Jakarta is operated by LRTJ, a subsidiary of Jakpro.
LRT Jakarta Phase 2A is an extension route from the existing, that connects Kelapa Gading to Jakarta International Stadium, consisting of an 8.2 km line serving 6 stations. Phase 2A development and construction will cost around IDR 467 trillion.

Investment Cost
IDR. 7,09 Trillion

Investment Opportunity : Public Private Partnership / Funding
Source of Revenue : Farebox & Non-Farebox
Current Status :
Route permit has been issued by the DKI Jakarta Provincial Government
Gross Floor Area : 8,2 kms infrastructure – 6 stations


Financial Analysis

Economic Internal Rate of Return : 13.3%
Economic Net Present Value : USD 8,449
Investment Rate of Return : 11.23%

Expected Start Date

2029

Location

JIS – Kelapa Gading

Contact Info

Name : Ririh Pratista
Job Title : Assistant Manager Transportation-LRT Project
Email : ririhpratista@jakpro.co.id


Other Projects