Project Overview

The project is part of the Jakarta Sewerage System program, which aims to develop and manage domestic wastewater treatment across 15 zones, including those currently in operation.

The primary objective of this project is to improve environmental conditions in Jakarta Zone 8 by collecting and treating 80% of the domestic wastewater generated in the service area and ensuring that the treated water complies with applicable environmental standards and regulations. The remaining 20% is expected to be managed through onsite septic tanks, supported by regular desludging and sludge treatment. Cumulatively, these efforts aim to achieve 100% sanitation coverage in Zone 8.

Market Opportunity :

  • 86.06% of respondents expressed willingness to obtain sewerage connections for their properties.

Target Market :

  • Service Coverage 840,779 PE
  • Potential Commercial Customers 166 units
  • Potential Household Customers 278,638 households
Investment Cost
IDR. 13,40 Trillion

Project Area : 6 Ha within 16 subdistricts across 3 districts
WWTP Area : 16,000 m3/day
Total Pipe Length : 949,400 m
Reticulation Sewer : 887 km
Relay Pumping Station PS-1 : 900L/s
WWTP, including pumping station PS-WWTP : 160 Mio L/day


Financial Analysis

Net Present Value : IDR 1.69 Tri
Investment Rate of Return : 12.15%
Discounted Rate : 9%

Expected Start Date

2027

Location

North Jakarta

-6.109870, 106.962498