IPALD Simatupang - Phase II





Project Overview

The construction plan for the sewer pipeline network and the Domestic Wastewater Treatment Plant (WWTP) in the TB Simatupang area is divided into two phases. The total planned length of the wastewater pipeline network is 7,616 meters, with a WWTP capacity of 6,000 m³/day. Service coverage for this project is 100.028 People Equivalent (PE). The wastewater treatment system will utilize the Moving Bed Biofilm Reactor (MBBR) technology.

Progress of the Phase I development plan has currently reached the tender preparation stage, with funding sourced from Regional Infrastructure Development Budget (PMD 2018) and scheduled for completion in the second quarter of 2026. For Phase II, the planned pipeline network covers 5,067 meters with a Mechanical & Electrical Capacity Upgrade of 2,000 m³/day.

Market Opportunity :

  • The service is designed to cover approximately 100,028 people

Target Market :

  • 57 unit commercial building (such as : Hospital, Office, Showroom, Clinic, Apartment, University, School, Hotel).
Investment Cost
IDR. 186,00 Billion

WWTP Area : 2,910 m2
Total Pipe Length : 5,067 m
Mechanical & Electrical Capacity Upgrade Phase II : 2,000 m3/day
Capacity WWTP Phase II : 6,000 m3/day


Financial Analysis

Net Present Value : IDR 13.3 Mio
Investment Rate of Return : 7.71%
Weighted Average Cost of Capital : 7.00%
Payback Period : 20 years

Expected Start Date

2026

Location

Cilandak Water Treatment Plant Perumda PAM Jaya Area (TB. Simatupang)

-6.293412, 106.806538

Contact Info

Name : Haris Faza Indrapta
Title : Perumda Paljaya B2B Team Member | Staf of Engineering Planning
Email : Harisfazaindrapta@gmail.com 