PT Jakarta Propertindo (Jakpro) has been mandated to develop LRT Jakarta Phase 2A. The project extends the existing LRT Jakarta Phase 1 line (Kelapa Gading–Velodrome) by 8.2 km, connecting Kelapa Gading to Jakarta International Stadium (JIS) and consists of 6 main stations; Kelapa Nias, Boulevard Gading, Sunter Timur, Gelanggang Remaja, Sunter Barat, and Danau Sunter Barat (Jakarta International Stadium).
| Willingness to Pay | IDR 10,000 – 15,000 per trip (Farebox) |
|---|---|
| Demand | 67,256 passengers per day |
| Age Range | 70% within age range 20-39 years old |
|---|---|
| Reason to Travel | 41% Recreation, 35% Business |
| Base Fare | IDR 3,000 per trip |
|---|---|
| Distance-based Fare | IDR 750 per km |
| Projected Naming Rights Revenue | IDR 10–33 Billion over 5 Years |
|---|---|
| Retail Revenue | IDR 375,000 – 562,500 per m2/month |
| Unit-Based Revenue | IDR 3.5-5.4 Million per unit/month |
| Advertisement Revenue | Station: IDR 660,000 per m2/year Train: IDR 213.5 Million per train/year |
| Partnership Scheme | G2G Loan, PPP, or EPCF |
|---|---|
| Investment Sharing | None |
2027
NPV : IDR 164.2 Billion
IRR : 12.3%
WACC : 12%
Payback Period : 15 years
Partnership Period: 10 years
Route Length : 8.2 km
Naming Rights : Up to 6 stations (Phase 2A)
Retail : Approximately 149 m2 of retail space per station
Unit Based : Up to 10 units/station
Station Advertisement Assets : 50 sqm/station
Train Advertisement Assets : Up to 32 trains (Phase 2A)
Kelapa Nias - Boulevard Gading - Sunter Timur - Gelanggang Remaja - Sunter Barat - Danau Sunter Barat (Jakarta International Stadium)
Name : Daru Pambayun Ramadhanti
Title : Officer Transportation - LRT Project